Calibre Construction Update

17 December 2014

For those who have driven past the Marque Maribyrnong site recently you would be well aware that Stage 1 – Calibre has taken shape rather quickly. As a show of the progression being made trades are now also turning their attention to the interiors and will continue pushing hard to achieve the anticipated completion date in 2015.

Construction Update outlined below;

  • Plasterers commenced.
  • Tilers commenced.
  • Window install underway.
  • Internal fitout underway.
  • You will see crown on top of the building early 2015.
  • Completion due MAY 2015.